Construction update:

Following an extensive redevelopment, the stadium was inaugurated in May 2017 ahead of the Amir Cup final. In 2019, the stadium hosted the IAAF World Athletics Championship and matches during the Arabian Gulf Cup and FIFA Club World Cup™.

Key facts:

Al Janoub Stadium

Al Janoub Stadium

Construction update:

The stadium was inaugurated in May 2019 when it became the first Qatar 2022 tournament venue to be built from scratch.

Key facts:

Education City Stadium

Construction update:

Construction work was completed in December 2019. The stadium is set to open this year.

Key facts:

Al Bayt Stadium

Construction update:

Construction work has been completed at the stadium, which will open this year. Al Bayt Park, situated in the stadium precinct, has opened.

Key facts:

Al Rayyan Stadium

Construction update:

The concrete frame and roof installation have been completed. Work on the upper-tier stands is approaching completion. More than half of the façade columns have been installed. The stadium is set to open this year.

Key facts:

Al Thumama Stadium

Construction update:

The stadium’s concrete frame and roof columns have been installed. Work on the upper-tier stands is approaching completion. Construction is due to be completed by the end of 2020.

Key facts:

Ras Abu Aboud Stadium

Construction update:

475 containers have been delivered to the site, while 90 have been installed so far. Steel fabrication for the structure is 50% complete. The fabrication of the bleachers, concourse slabs and roof steel are progressing. Construction work set to be completed in 2020.

Key facts:

Lusail Stadium

Construction update:

The superstructure’s concrete and steel works have been completed, along with the stadium’s external primary steel works. Significant progress has been made in relation to the mechanical, electrical and plumbing works inside the structure. Stadium set to be completed in 2021.

Key facts: